Module III·Article II·~2 min read

Liability for Breach of Contract and Remedies

Contract Law

Turn this article into a podcast

Pick voices, format, length — AI generates the audio

Types of Breach of Contract

Non-performance — complete refusal to fulfill the obligation.
Improper performance — performance that violates the terms (delay, defects, incomplete volume).
Anticipatory breach — a clear statement by a party that it will not perform the contract. In common law, this allows the other party to sue immediately without waiting for the due date.

Remedies

Damages — the main remedy. The goal is to put the injured party in the position they would have been in had the contract been properly performed.

  • Actual damages (direct losses)
  • Lost profits
  • Moral damages (only for individuals in most systems)

Limitations: (1) Causation; (2) Foreseeability of losses at the time of entering into the contract (the rule from Hadley v. Baxendale); (3) Duty of the injured party to mitigate damages.

Liquidated Damages / Penalty Clause — a pre-agreed amount for breach. In Russia — fine or penalty. In common law — liquidated damages (a reasonable pre-estimate of loss) are valid; penalty clauses (punitive penalties) — courts may reduce.

Specific Performance — the court requires the breaching party to perform the contract. Applied when monetary compensation is insufficient (unique goods, real estate).

Termination/Rescission — the parties return to their original positions. Applied in case of material breach.

Force Majeure and Change of Circumstances

Force Majeure — circumstances of irresistible force (war, natural disaster, epidemic), making performance impossible. Upon the occurrence of force majeure, the party is released from liability, but not from the obligation. COVID-19 generated thousands of disputes over force majeure.

Hardship (Significant Change of Circumstances) — performance of the contract has become excessively burdensome (but not impossible). Requires negotiations and possible revision of the contract.

Practical Task

A construction contractor was six months late in completing a project due to rising prices for materials. The contract contains a penalty of 0.1% of the contract price for each day of delay. Analyze: (1) Is the increase in prices a force majeure? (2) Can the contractor demand a revision of the price? (3) How can the penalty be reduced in court?

§ Act · what next